April progress at our Ten-Billion-Capsule Plant

writer:

April 29, 2026

April progress at our Ten-Billion-Capsule Plant:
✅ All 3 Workshops
Interior/exterior plastering, flooring, and roofing nearing completion
True-stone façade painting in full swing
Windows, doors, railings — all installed
✅ MEP Installations at Peak
Ductwork, fire piping, cable trays, electrical panels, lighting, alarm systems — all actively underway
Power & signal wiring fully progressing
✅ Site Infrastructure
Stormwater main line completed; valve pits constructed
Road base course laid; temporary entrance operational
➡️ Façade taking shape. MEP systems accelerating. Equipment installation next!

20260429-170157.jpg

Related news

Subscribe To Our Emails

Headoffice

Room 2403, Tower B, Boee Building, Minhe Road No.836, Xiaoshan District, Hangzhou, Zhejiang, 310000, China

Factory

Ru'ao Industrial Zone, Xinchang, Shaoxing, Zhejiang, 312500, China

Telephone

+86-571-85450076

Mail

inquiry@wecaps.com
© 2024 Beyondsun Supported by MFSHOP